CategoryPlantTypeClientCapacityCountryLocationScope
of Work
Completion
Gas Processing Plants and LNG/LPG Terminals Floating Production Unit (FPU) -- ENI Muara Bakau B.V.

150 x 3 (MMSCFD)

Indonesia Jangkrik Gas Field E.P.C.I. (2017)
Gas Processing Plants and LNG/LPG Terminals LNG Plant Train-3 BP Berau Ltd. 3.8(MMTY) Indonesia West Papua FEED 2016
Gas Processing Plants and LNG/LPG Terminals LNG Plant FLNG INPEX Masela, Ltd. 2.5(MMTY) Indonesia Abadi Gas Field FEED 2014
Gas Processing Plants and LNG/LPG Terminals Acid Gas Removal aMDEA PetroChina International Jabung Ltd.  Process Indonesia Jambi E.P.C. 2005
Gas Processing Plants and LNG/LPG Terminals Gas Processing Plants Gas
Processing
Plant
PetroChina International Jabung Ltd. Sales Gas 100MM SCFD
LPG 15,200 BPSD
Condensate 9,930 BPSD
(T/Y)
Indonesia Jambi E.P.C. 2005
Gas Processing Plants and LNG/LPG Terminals Gas Processing Plants Modernization of Control System PT. Badak Natural Gas Liquefaction -- Indonesia Bontang B.E.P.C.M. 2002
Gas Processing Plants and LNG/LPG Terminals LNG Plants (EPC) DCS Retrofit & Instrumentation Upgrade PT. Badak Natural Gas Liquefaction -- Indonesia Bontang E.P.C.M. 2002
Gas Processing Plants and LNG/LPG Terminals Gas Processing Plants LNG/LPG Plant (Train I) PERTAMINA LNG 2,950,000
LPG 83,000
(T/Y)
Indonesia Bontang FEED 2001
Gas Processing Plants and LNG/LPG Terminals LNG Plants (FEED/PS) Train-l PERTAMINA 2.95
(MMTY)
Indonesia Bontang FEED 2001
Gas Processing Plants and LNG/LPG Terminals LNG Plants (FEED/PS) Train 1 & 2 PERTAMINA / BP Berau, Ltd. 3.3 x 2
(MMTY)
Indonesia Tangguh FEED 2001
Gas Processing Plants and LNG/LPG Terminals Acid Gas Removal aMDEA PERTAMINA (Train I)  Process Indonesia Bontang FEED 2001
Petroleum Refineries Catalytic Reforming Units Platforming PERTAMINA *20,000
(Restoration)
(BPSD)
Indonesia Balikpapan E.P.C. 2001
Gas Processing Plants and LNG/LPG Terminals Acid Gas Removal a MDEA PERTAMINA / BP Berau Ltd.  Process Indonesia Irian Jaya FEED 2001
Gas Processing Plants and LNG/LPG Terminals LNG Plants (EPC) No.3 Loading Dock Perusahaan Pertambangan Minyak Dan Gas Bumi Negara (PERTAMINA) -- Indonesia Bontang E.P.C. 1999
Photovoltaic Power Plants, Green Device and Non-Ferrous Metal Plants Non-Ferrous Metal Plants Copper Cathode Plant P.T. Smelting Co. 200,000 ton/year Indonesia -- E.P.C. 1998
Gas Processing Plants and LNG/LPG Terminals LNG Terminals Storage & 3rd Loading Facilities PERTAMINA -- Indonesia Bontang E.P.C. 1998
Petrochemical and Chemical Plants Engineering Plastics Polyethylene Terephtalate (PET) Teijin Indonesia Fiber Co. -- Indonesia Tangenang E.P.C. 1998
Gas Processing Plants and LNG/LPG Terminals LPG Terminals Storage & 3rd Loading Facilities PERTAMINA -- Indonesia Bontang E.P.C. 1998
Petrochemical and Chemical Plants Fertilizer Plant Urea P.T. Pupuk Kalimantan Timur (KALTIM) -POPK A 1,725
(T/D)
Indonesia Bontang B.E.P.CS.M.T. 1998
Gas Processing Plants and LNG/LPG Terminals Acid Gas Removal aMDEA PERTAMINA (Train G)  Process Indonesia Bontang E.P.C.M. 1997
Gas Processing Plants and LNG/LPG Terminals LNG Plants (EPC) Train G Perusahaan Pertambangan Minyak Dan Gas Bumi Negara (PERTAMINA) 2.3
(MMTY)
Indonesia Bontang E.P.C.M. 1997
Petrochemical and Chemical Plants Aromatics Terephthalic Acid PT. Amoco Mitsui PTA Indonesia CTA 350,000
(T/Y)
Indonesia Merak E.P.C. 1997
Petrochemical and Chemical Plants Aromatics Terephthalic Acid PT. Amoco Mitsui PTA Indonesia PTA 350,000
(T/Y)
Indonesia Merak E.P.C. 1997
Petrochemical and Chemical Plants Others Sorbitor PT. Sorini Towa Berlian Co. 7,000
(T/Y)
Indonesia Surabaya E.P.C. 1996